High Capacity Power Transmission Corridors - Connecting India on a Common Grid
High Capacity Power Transmission Corridors - Connecting India on a Common Grid

Corridor | Schedule | Status as on March 31,2013 |
HCPTC-1
IPPs in Orissa |
Major project elements May 2014-July 2014
Balance: By December 2015 |
All awards placed.
Engineering Survey and construction in progress Private portion of corridor through Tariff Based Competitive Bidding (TBCB) awarded to Sterlite. |
HCPTC - 2
IPPs in Jharkhand, West Bengal |
Progressively from November, 2013 to November, 2014 | About 78% works awarded.
In awarded packages Engineering Survey and construction work under progress Award of balance packages under progress and expected in 2013-14 progressively. Private portion of corridor through Tariff Based Competitive Bidding (TBCB) awarded to Sterlite. |
HCPTC - 3
IPPs in Sikkim |
Progressively from November, 2013 to March, 2014 | All works awarded.
Engineering Survey and construction in progress |
HCPTC - 4
IPPs in Chhattisgarh and Madhya Pradesh |
November, 2013 | All works awarded.
Engineering Survey and construction in progress |
HCPTC - 5
IPPs in Chhattisgarh |
Progressively from May, 2013 to December, 2015 | 85% works awarded.
In awarded packages Engineering Survey and construction works in progress Award of balance packages under progress and expected in 2013-14 progressively. Private portion of corridor through Tariff Based Competitive Bidding (TBCB) awarded to Sterlite. |
HCPTC - 6
IPPs in Krishnapatnam, Andhra Pradesh |
September, 2014 | All works awarded.
Engineering Survey and construction in progress |
HCPTC - 7
IPPs in Tuticorin, Tamil Nadu |
Progressively from July, 2014 to December, 2014 | All works awarded.
Engineering Survey and construction in progress |
HCPTC - 8
IPPs in Srikakulam, Andhra Pradesh |
Progressively from June, 2015 to December, 2015 | About 50% pkgs awarded.
In awarded packages, Engineering Survey and construction in progress Award of balance packages under progress and expected in 2013-14 progressively. |
HCPTC - 9
Common Corridor for transfer of power SR IPPs to WR/NR |
2016-17 | On Hold due to poor progress of SR IPPs. |
HCPTC - 10
IPPs in Vemagiri, Andhra Pradesh |
Progressively from i May,2014 to March, 2015 | Tendering under progress.
Part of Private portion of corridor through Tariff Based Competitive Bidding (TBCB) awarded to POWERGRID. |
HCPTC-11
IPPs in Nagapattinam, Tamil Nadu |
Progressively from May,2014 to March, 2015 | Tendering under progress.
Part of Private portion of corridor through Tariff Based Competitive Bidding (TBCB) awarded to POWERGRID. |
Source: Cerebral Business Research Pvt. Ltd.
Author Profile
Subscribe to:
Post Comments
(
Atom
)
Thank you so much sharing such a very nice information..
ReplyDeletePower Transformers in India | Transformer Manufacturer in India
thank you for sharing nice information.
ReplyDeletesolar developers in India
grid connected solar pv system
Thanks for sharing the valueable information about. High Capacity Power Transmission Corridors - Connecting India on a Common Grid. Really it's a great blog. For knowing more you can visit https://www.sterlitepower.com/
ReplyDelete