Analysed outcome on Design and Performance of Chinese Equipment by CEA

Central Electricity Authority has done two studies on Design and Performance of Chinese Equipments. The two studies made were, the first one included Design Features of Boilers and Auxiliaries being sourced from Chinese Manufacturers in year 2008. The second one was to Analyze the performance of Chinese equipment vis-a-vis Indian equipment in year 2013
Details of Study on Design Features of Boilers and Auxiliaries from Chinese sources.
  • The Study Covered 5 stations with 300/330 MW and 2 stations with 600 MW . units (All Sub-critical)
    • 300/330 MW Units - Yamunanagar- HPGCL, Durgapur- DPL, Sagardighi- WBPDCL, Lanco-Amarkantak, Mundra-Adani Power.
    • 600 MW Units- Lanco Anapara C, Hissar HPGCL.
  • Only 3 Commissioned Stations - Yamunanagar, Durgapur & Sagardighi.
  • Main Findings in this study.
    • The technical particulars relating to major design features of boiler and their auxiliaries found to be in line with good engineering practices- any generic design issues could be best known after these units operate for an initial period of about one to two years.
    • Initial 1-2 years of operation of any plant are critical and will bring out inherent generic deficiencies, if any.
    • Operational feed back then available indicated milling Constraints in some units
    • Secondary fuel oil consumption has been found to be high in all the three operational projects.
    • Layout constraints Found in some of the plants which may result in difficulties in attending to the equipment during maintenance.
    • Data Gaps- No information from Chinese manufacturers on design features, operational performance, Standards followed during manufacturing & testing procedures. Lack of Sufficient data with plant owners.
    • Some of the utilities did not have complete information about important technical particulars -During interaction with the project authorities of the three operating stations, it has emerged that there has been substantial lack of participation by the utilities in the areas of technical specifications, detailed engineering, quality inspection at works, erection supervision, training of O&M personnel, etc.
    • Important equipment drawings/ technical data/ documents were not available with the projects. Design data was also not available with some IPPs sourcing the equipment from Chinese manufacturers.
  • Recommendations - Need for due diligence
    • Due diligence required by the utilities during stage of specification finalization and detailed engineering, inspections/testing etc. to minimize O&M problems
    • Detailed comprehensive quality plans for ensuring quality at works and at site identifying customer hold points and test procedures and Standards needs to be defined and implemented for each major equipment/system. Some of the utilities were found lacking in this regard
Details of study to Analyse the performance of Chinese equipment vis-a-vis India Equipment.
  • A study to Analyse the performance of Chinese equipment vis-a-vis Indian equipment was taken up by CEA in 2011 - through a Committee of CEA and NTPC.
    • The Objective of the study was to analyse the performance of Chinese equipment vis-avis Indian equipment (BHEL) including coal consumption patterns, heat rate and efficiency achieved.
    • Areas Covered
      • Operating Load Factor (OLF), Outages/Downtime
      • Design Parameters- Turbine cycle Heat rate & Boiler Efficiency Flow Margins
      • Operating Efficiency - Heat Rate and Specific Fuel Oil Consumption
      • Problems in Erection & Commissioning
  • Units Considered in Study 2  
    • The Study covered Chinese Subcritical units of 300 and 600 MW and BHEL Sub-critical units of 250 and 500 MW units commissioned in 11th Plan (2007-08 to 2010-11)
    • Chinese capacity covered - 8200 MW
      • 22 Units across 11 stations
    • BHEL capacity Covered -12480 MW
      • 36 Units across 22 Stations
Chinese Make Units. Indigenous (BHEL) Units
Unit Size Units Stations Unit Size Units Stations
300 MW 13 7 250 MW 22 12
330 MW 4 1 500 MW 14 10
600 MW 5 3
  • Study-2: Details of Manufacturers
    • Manufacturers Wise Break up of Capacity
Supplier  Boiler Supplied TG Supplied
Nos. Capacity Nos. Capacity
Dongfang China 6 2100 8 3300
SEC China 10 3600 10 3600
Babcock Wilcox China 4 1320 0 0
Beijing Beizhong STG China 0 0 4 !320
Harbin China 2 1200 0 0
BHEL India 36 12480 36 12480
  • Thus Most Chinese Supplies from Dongfang and Shanghai (SEC).
  • Main Finding - Steam Parameters & Heat Rate
    • Steam parameters and Design Turbine cycle heat rate
S. No Stations /Unit Size MS Pressure Temperature MST/RHT Turbine cycle heat rate Remarks
1 Chinese 300 MW units 1701 537/537 1910 The Design Heat rate for Chinese units do not correlate well with the steam flows indicated and large variations in design steam flows are seen for similar
2 Chinese 600 MW units 170 537/537 1954
3 BHEL 250 MW Units 150 537/537 1945
4 BHEL 500 MW Units 170 537/537
537/565
1945
1936
The regenerative system configuration of Chinese machines is different from BHEL machines and Chinese 300 MW units have higher steam Pressure also. Thus on like to like comparison basis the BHEL machines indicate higher cylinder efficiency implying that their design/construction in terms of blading provided, sealing etc. renders higher efficiency
Expected THR of BHEL machine with similar configuration - 1890 (250 MW) and 1932/1920 (500 MW)
  • Main Findings - Flow Margins
Both, the Chinese 300 & 600 MW and BHEL 250 & 500 MW units have adequate flow margins - VWO and BMCR margins. However the Chinese 330 MW machines have a composite TMCR to BMCR margin of 5.34 % which is very low and not compliant to the CEA Technical Standards and may not meet IEGC provisions.
  • Main Findings -Outages and Load Factors
Operating Load factors and Outages
S. No Stations Operating Load Factor (%) Total Outages (%) Remarks
1 Chinese units -Domestic Coal 512 23.5 Chinese units based on domestic coal have higher outages and lower load factors than imported coal based units as well as BHEL units
2 Chinese units -Imported Coal 80.4 14.1
3 BHEL Units Domestic Coal 71.6 18.7
CEA Monitoring Data
PLF - 2011-12 (units in Study) - Chinese (D) -66.19, (I) 75.46, BHEL- 76.68
PLF - 2012-13 (units in Study) - Chinese (D) -52.27, (I) 81.57, BHEL- 78.13
  • Main Findings - Operating Heat Rate
S. No Stations Operations Heat Rate Remarks
kcal/kWh Dev. from Design (%)
1 Chinese units Domestic Coal 2719 23.29 Chinese units based on domestic coal. Have higher Operating Heat Rate than Chinese imported coal based units as well as BHEL units.
2 Chinese units Imported Coal 2275 4.71
3 BHEL Units Domestic Coal 2520 12.77
Chinese imported coal based units show much lower heat rate than indigenous coal based units - the difference is far higher than envisaged due to the boiler efficiency difference.
Variations in Operating Heat Rate of BHEL units are seen. Six stations show operating deviation (below 5%, four stations show deviation of around 10-11 %. Rest of the stations show very high deviations of 15-25 % and even higher.
Chinese indigenous coal based units generally show high operating deviations.
  • Main Finding - Specific Secondary Fuel Oil Consumption (SFC)
S. No Stations SFC Remarks
1 Chinese units Domestic Coal 6.13 BHEL Units show remarkably better SFC than Chinese indigenous coal based units
2 Chinese units Imported Coal 1.34
3 BHEL Units Domestic Coal 3.06
SFC for Chinese imported coal based stations is considerably lower than indigenous coal based stations. Indigenous - 2.5 to 5 ml/kWh. Best Yearly values Indigenous- 0.90, Imported- 0.53.
Large number of BHEL supplied stations show very low SFC of below one ml/kWh. The lowest overall (2007-11) SFC is 0.27 ml/kWh followed by 0.47, 0.52, 0.54 and 0.81 ml/kWh.
The yearly SFC for individual BHEL stations are even lower. The best yearly SFC is 0.16 ml/kWh followed by several instances of yearly SFCs in the range of 0.20 to 0.50 ml/kWh.
  • Station Visits
    • Visits to Stations
  • BHEL stations - Generally satisfied
  • Chinese Stations - Mixed Bag. Widely different feedback from two stations visited.
  • Main Finding - Turbine Control Systems
The level of automation in Chinese turbines is much less than the BHEL turbines The Chinese turbines do not have many analysis/diagnostic functions and equipment safety features such as Turbine Stress Evaluator (TSE) and Auto Turbine Run-up Systems (ATRS) in their control system. Thus, lot of manual interventions are envisaged during start up as well as during normal operation of Chinese machine contrary to philosophy of fully automated system with minimum manual intervention in BHEL machines.
Thus the control systems of Chinese turbines are not in line with the prevailing modern turbine design/technology. Manual intervention during critical operations gives rise to subjectivity with the possibility of mal-operation and accidents.

Author Profile

1 comment :

  1. Good-day, I'm Josef Lewis. A reputable, legitimate & accredited lender. We give out loan of all kinds in a very fast and easy way, Personal Loan, Car Loan, Home Loan, Student Loan, Business Loan, Inventor loan, Debt Consolidation. etc

    Get approved for a business or personal loans today and get funds within same week of application. These personal loans can be approved regardless of your credit and there are lots of happy customers to back up this claim. But you won’t only get the personal loan you need; you will get the cheapest one. This is our promise: We guarantee The lowest rate for all loans with free collateral benefits.

    We strive to leave a positive lasting impression by exceeding the expectations of my customers in everything I do. Our goal is to treat you with dignity and respect while providing the highest quality service in a timely manner. No social security Number required and no credit check required, 100% Guaranteed. Kindly respond immediately using the details below if interested in a loan and be free of scams..

    Email: progresiveloan@yahoo.com
    Call/Text +1(603) 786-7565 thanks



    ReplyDelete