Proposed Amendments to Tariff Policy Under Electricity Act 2003

Proposed Amendments to Tariff Policy Under Electricity Act 2003

The existing tariff policy has recently been reviewed by the expert committee and the following necessary amendments have been proposed in the Tariff Policy under section 3 of Electricity Act 2003.  Following are the proposed amendments to the act which might give us a food for thought regarding the existing tariff policy. For your Reference you may download the existing policy and Amendment from the links below.
Amendment: 8.3(1) In accordance with the National Electricity Policy, consumers below poverty line who consume below a specified level, say 30 units per month, may receive a special support through cross subsidy. Tariffs for such designated group of consumers will be at least 50% of the average cost of supply. This provision will be re-examined after five years.
Justification: The review of the above clause was considered by the Working Group and observed that no modification of the clause is required and hence, the same provision can be continued further and therefore the phrase "This- provision will be re-examined after five years" is now required to be deleted.
Amendment: 8.5.1- National Electricity Policy lays down..........is used to bring about competition in the larger interest of consumers. Accordingly, when open access is allowed the surcharge for the purpose of sections 38,39,40 and sub-section 2 of section 42 would be computed as the difference between (i) the tariff applicable to the relevant category of consumers and (ii) the cost of the distribution licensee to supply electricity to the consumers of the applicable class. In case of a consumer opting for open access, the distribution licensee could be in a position to discontinue purchase of power at the margin in the merit order.
Accordingly, the cost of supply to the consumer for this purpose may be computed as the aggregate of (a) the weighted average of power purchase costs (inclusive"of fixed and variable charges) of top 5% power at the margin, excluding liquid fuel based generation, in the merit order approved by the SERC adjusted for average loss compensation of the relevant voltage level and (b) the distribution charges determined on the principles as laid down for intra-state transmission charges.
Surcharge formula:
S = T - [ C (1+ L / 100) + D ]
Where
S is the surcharge
T is the Tariff payable by the relevant category of consumers;
C is the Weighted average cost of power purchase of top 5% at the margin excluding liquid fuel based generation and renewable power
D is the Wheeling charge
L is the system Losses for the applicable voltage level, expressed as a percentage

The cross- subsidy surcharge should be brought down progressively and, as far as possible, at a linear rate to a maximum of 20% of its opening level by the year 2010-11.
Accordingly, an alternative formulation for calculating cross subsidy surcharge could be worked out to ensure that neither open access is throttled nor does the host DISCOM unduly suffer.
SERCs may calculate Cross-Subsidy Surcharge based on the assumptions that the power available as a result of exit of open access consumer will be sold at the average revenue realization rate. This appears to be the most practical scenario in a situation of shortage of power supply. The SERCs may assume certain percentage (say 10%) of the total consumption by eligible open access consumers for the purpose of estimation of power available for sale at average realization rate. The wheeling . charge (grossed up by the system loss at appropriate level) to be recovered from the open access consumers should also be factored into computation of surcharge. At the same time it should also be ensured that the formula incentivizes the distribution licensees to reduce their distribution losses.
For a situation where there is no power cut, SERCs may calculate Cross-Subsidy Surcharge based on the estimation that the DISCOM will avoid purchase of the quantum of power for which open access has been sought. This principle of avoided cost method should be adopted in areas where there are no power shortages. Other assumptions relating to quantum of power avoided and the wheeling charges could be on the same lines as above.
Justification: An opinion was-expressed for review of the formula given in the Tariff Policy which uses the weighted average cost of power purchase of top 5 % as a factor and leads to a negative cross subsidy surcharge in certain cases. Allowing consumers to migrate to open access under these conditions increases the burden of the DISCOM and this was not in line with the spirit of the cross - subsidy surcharge as per the Tariff Policy. There is thus a need to re-determine the formula for calculating cross subsidy surcharge. The options suggested were based on the average cost or bottom 5% costs.
Section 61 (g) of the Electricity Act, 2003 provides that appropriate Commission shall determine tariff keeping in view the factor that the tariff progressively reflects the cost of supply of electricity and also, reduces cross-subsidies in the manner specified by the Appropriate Commission. However, very few SERCs have specified the roadmap of reduction of cross subsidies. Therefore, roadmap of reduction of cross subsidies should be specified by SERCs in line with the spirit of the Act.
Amendment: 8.5.6 In case of outages of generator supplying to a consumer on open access-----standby arrangements should be provided by the licensee on the payment tariff for temporary connection to that consumer category as specified by the Appropriate Commission. charges may be decided by mutual agreement between the open access consumers and the distribution companies.
Justification: The issue of Universal Service Obligation (USO) and standby charges was taken up by the Task Force on Operationalisation of Open Access in the Planning Commission with the M/o Law & Justice.
After consultation with M/o Law & Justice/Ld. Attorney General of India Ministry of Power had issued clarification vide letter dated 30.11.2011 that "all 1MW and above consumers are deemed to be open access consumers and that the regulator has no jurisdiction over fixing the energy charges for them". All concerned have been requested to take necessary. steps for implementing the provisions relating to open access in the Electricity Act, 2003 in light of the said opinion.
Amendment: Para 8.4: 1(iii) It will take some time before non- conventional technologies can compete with conventional sources in terms of cost of electricity. Therefore, procurement by distribution companies shall be done at preferential tariffs determined by the Appropriate Commission.
2. Such procurement by Distribution Licensees for future requirements shall be done, as far as possible, through competitive bidding process under Section 63 of the Act within suppliers offering energy from same type of non-conventional sources. In the long- term, these technologies would need to compete with other sources in terms of full costs. Short term procurement through Purchase of Renewable Energy Certificates (REC) or at preferential tariffs.
Justification: In order to bring more competition to the Renewable Energy sector with consequent reduction in prices of power production through the renewable sources of energy, the following options were deliberated:

  • Long term procurement of power by the distribution licensee to be done only through competitive bidding process (CBP) .and Power Purchase Agreements (PPA). 
  • REC Mechanism has already been launched by CERC which along with the preferential tariffs takes care of the short, term procurement by the distribution licensees.

In the absence of competitive bidding for long term procurement from renewable energy sources there will be no competition in the sector and consumer will be deprived of the competitive rates for renewable energy.
Amendment: Para 6.4: Pursuant to provisions of section 86(1 )(e) of the Act, the Appropriate Commission shall fix a minimum percentage of the.....obligations. In view of the comparatively higher cost of electricity from solar energy currently, the REC mechanism should also have a solar specific REC. (iii) It will take some time before non- conventional technologies can compete with conventional sources in terms of cost of electricity. Therefore, procurement by distribution companies shall be done at preferential tariffs determined by the Appropriate Commission. Long term trajectory for RPO for the development of renewable energy to be prescribed by the Appropriate Commission.
Justification: Renewable Purchase Obligation (RPO) is fundamental to the growth of renewable energy as without this commitment, given higher cost of renewable energy, the States may not be willing to purchase such power. In order to meet the targets set up under the National Action Plan on Climate Change (NAPCC) the States should strive to make mandatory RPO equivalent to the minimum as per the NAPCC targets.
Stable RPO regime is a pre- requisite for promotion of renewable energy sources. The long term trajectory for Renewable Purchase Obligation would give greater visibility for the market players to plan their investment in the Renewable Energy Sector.
It is desirable that States should formulate long term trajectory for RPO for the development of renewable energy sector.
Amendment: Para 7.1 (6): However, in the following cases the exemptions from competitive bidding route may be adopted:

  1. 1200 kV EHVAC and HVDC systems upto 13th Plan i.e. year 2021-22, after which it shall be reviewed for introduction of competitive bidding.
  2. Works required to be done by CTU/STUs to cater to an urgent situation or, which are required in a compressed time schedule by CTU/STUs or, which are of National importance/backbone of National Grid, as decided by Central Government on case to case basis.
  3. The intra-state transmission projects by STUs will be exempted from competitive bidding route for further 2 years beyond 6.1.2011.
  4. Transmission scheme with estimated project cost less than Rs. 200 crores. This limit could be reviewed by the Ministry of Power from time to time.

Justification: There is a difference between the technology for 1200 kV EHVAC lines and sub-stations and HVDC stations and bipole. This involves different sets of equipments. Therefore as recommended by Empowered Committee it would be desirable to seek exemption from 1200 kV EHVAC system separately.
CEA is of the view that considering the technical complexity involved in the HVDC converter stations and the importance of control of flow of power in the HVDC converter stations in the national grid CEA is of the view that it should be exempted from tariff based competitive bidding route. HVDC bipole lines alongwith the converter stations form a complete system as a whole, and hence should not be seen in isolation, so both the bipole as well as convertor stations may be exempted from the realm of competitive bidding.
In its 30th meeting held on 31.10:2012 the Empowered Committee had recommended that projects costing less than Rs. 200 crores may be implemented through regulated tariff mechanism as small schemes are not amenable to tariff based competitive bidding as reputed parties may not be interested due to high overheads and the need for setting up independent O&M for 35 years.
Amendment: Clause 5.1 (d): Long-term PPA would be at least for 60% of the total saleable design energy. However, this figure of 60% would get enhanced by 5% for delay of every six months in commissioning of the last unit of the project against the scheduled date approved by the Appropriate Commission before commencement of the construction. The graded reduction in % of allowable merchant sales be limited to delays attributable to the developer. The time period for commissioning of all the units of the project shall be four years from the date of approval of the commissioning schedule by the Appropriate Commission. However, the Appropriate Commission may, after recording reasons in writing, fix longer time period for large storage projects and run-of-river projects of more than 500 MW capacity. Adherence to the agreed timelines to achieve the fixed commissioning schedule shall be verified through independent third party verification through a mechanism prescribed by the Central Government.
The graded reduction in % of allowable merchant sales may not be completely dispensed with since the provision of merchant power has been extended as an incentive for timely completion of projects. However, it is also felt that the provision to reduce the permitted percentage of merchant sale for delays in commissioning of the project, the total delay may be limited to the delay which is attributable to the Developer. 
Justification: It has been observed over time that hydro projects are prone to time and cost over runs due the reasons which are beyond the control of the developers. Over the past few years IPPs have been raising the issue of reduction in maximum permissible limit of Merchant Sale in Hydro Projects (i.e. 40%) on account of delay in Project construction beyond six months @ 5% for delay of every six months in commissioning of the last unit of the project. The IPPs have assigned various reasons for delay in commissioning the units including inter-alia geological surprises, R&R issues, law & order problems etc. They have represented that they ought not to be penalized for reasons which are beyond their control. During the 5th meeting of the Hydro Task Force some State Govts have raised the aforesaid issue of reduction in maximum permissible limit of merchant sale on account of delay in commissioning of projects.
The Division had suggested that notwithstanding the inherent uncertainties in completion of hydro projects as mentioned above, the graded reduction in % of allowable merchant sales may not be completely dispensed with since the provision of merchant power had been extended as an incentive for timely completion of projects. However, it is also felt that reduction in % of allowed merchant sale may be limited to the delay attributable to the Developer.

The graded reduction in % of allowable merchant sales may not be completely dispensed with since the provision of merchant power has been extended as an incentive for timely completion of projects. However, it is also felt that the provision to reduce the permitted percentage of merchant sale for delays in commissioning of the project, the total delay may be limited to the delay which is attributable to the Developer. 




Author Profile

No comments :

Post a Comment